Capital Improvement Project
Medina Central School District
► Capital Improvement Project
Our first project for Medina Central School District was a $34 million renovations project completed in 2020. As our first phase of CM services, Campus provided project planning and public information campaign assistance to prepare for a successful referendum. The project was presented to voters in two separate propositions. The first proposition included renovations to address high-priority facilities and program needs. The second proposition included an expansion to the District's athletic facility, Veterans Memorial Park, known among the community as "Vets Park." Upon a successful vote, Campus provided pre-construction, construction, and close-out phase services to deliver the project.
Veterans Memorial Park Reconstruction & Expansion
- New synthetic turf field
- Additional lighting
- Fence replacement
- New scoreboard
- New press box
- Reconfigured bleacher system
- Baseball/softball field reconfiguration
- Rebuild existing drainage system beneath turf field
- ADA code compliance features at Concession Stand
The following video of the Vets Park improvements was produced by the District's AV students:
Additional work featured in the project:
Medina High School
- Fire alarm system replacement
- Replace doors & hardware to meet code requirements
- Heating and cooling upgrades for air quality improvement
- Science Department renovations
- Library improvements
- Renovate multi-toilet facilities
- Band storage facility
- Repair / reconstruction of greenhouse
- Reconstruction of JV baseball & JV softball fields
- New 6-lane track & improvements to surrounding areas
Clifford Wise Intermediate / Middle School
- Cafeteria / serving area upgrades
- Fire alarm system replacement
- Replace doors & hardware to meet code requirements
- Repair pool roof by skylights & interior panels
- Replace upper pool windows & gymnasium windows
- Foundation / crawl space work
- Heating and cooling upgrades for air quality improvement
- Auditorium renovations
- Renovate multi-toilet facilities
- Reconstruct science room
Oak Orchard Elementary School
- Cafeteria / serving area upgrades
- Fire alarm system replacement
- Replace doors & hardware to meet code requirements
- Renovate toilet rooms at Auditorium
- Window replacement
- New emergency generator
- Heating and cooling upgrades for air quality improvement
- Renovate multi-toilet facilities
- New classroom casework
- Asbestos abatement
- New computer network operations center
Bus Garage
- Replace outdated bus lifts
- Provide a fire alarm system
Site Work
- New campus access road between Oak Orchard and Clifford Wise
- New sidewalks
- Parking & road lighting
- Relocate playground
- Drainage & utility relocation