Capital Improvement Project

Medina Central School District

► Capital Improvement Project

Our first project for Medina Central School District was a $34 million renovations project completed in 2020. As our first phase of CM services, Campus provided project planning and public information campaign assistance to prepare for a successful referendum. The project was presented to voters in two separate propositions. The first proposition included renovations to address high-priority facilities and program needs. The second proposition included an expansion to the District's athletic facility, Veterans Memorial Park, known among the community as "Vets Park." Upon a successful vote, Campus provided pre-construction, construction, and close-out phase services to deliver the project.

Veterans Memorial Park Reconstruction & Expansion

  • New synthetic turf field
  • Additional lighting
  • Fence replacement
  • New scoreboard
  • New press box
  • Reconfigured bleacher system
  • Baseball/softball field reconfiguration
  • Rebuild existing drainage system beneath turf field
  • ADA code compliance features at Concession Stand

The following video of the Vets Park improvements was produced by the District's AV students:

Additional work featured in the project:

Medina High School

  • Fire alarm system replacement
  • Replace doors & hardware to meet code requirements
  • Heating and cooling upgrades for air quality improvement
  • Science Department renovations
  • Library improvements
  • Renovate multi-toilet facilities
  • Band storage facility
  • Repair / reconstruction of greenhouse
  • Reconstruction of JV baseball & JV softball fields
  • New 6-lane track & improvements to surrounding areas

Clifford Wise Intermediate / Middle School

  • Cafeteria / serving area upgrades
  • Fire alarm system replacement
  • Replace doors & hardware to meet code requirements
  • Repair pool roof by skylights & interior panels
  • Replace upper pool windows & gymnasium windows
  • Foundation / crawl space work
  • Heating and cooling upgrades for air quality improvement
  • Auditorium renovations
  • Renovate multi-toilet facilities
  • Reconstruct science room

Oak Orchard Elementary School

  • Cafeteria / serving area upgrades
  • Fire alarm system replacement
  • Replace doors & hardware to meet code requirements
  • Renovate toilet rooms at Auditorium
  • Window replacement
  • New emergency generator
  • Heating and cooling upgrades for air quality improvement
  • Renovate multi-toilet facilities
  • New classroom casework
  • Asbestos abatement
  • New computer network operations center

Bus Garage

  • Replace outdated bus lifts
  • Provide a fire alarm system

Site Work

  • New campus access road between Oak Orchard and Clifford Wise
  • New sidewalks
  • Parking & road lighting
  • Relocate playground
  • Drainage & utility relocation

Owner: 
Architect: 
Gordon W. Jones Architects
Location: 
Medina, NY
Budget: 
$34.0M
Services: 
Construction Management | Referendum Planning | Estimating
Completion: 
2020